1920s reclamation - Ap lei chau [1922- ]
Primary tabs
Submitted by Admin on Thu, 2015-11-26 17:00
Current condition:
In use
Date Place completed:
1922-01-31
GW writes:
According to the PWD Reports of 1920-22, the contract was awarded in 1920 with work due to start in December that year, the sea walls were done by the end of 1921 , and the job was finished on 31st January 1922.